Cote Mateve Spread Mooring System with Ship-to-Ship Connectors
The Cote Mateve Spread Mooring system with Ship-to-Ship Connectors brought together the Tango FLNG and Excalibur FSU with a split mooring configuration – an industry first for a floating LNG terminal. This project’s tight timeline led to the development of the BarMoor® and BarLink mooring options, providing our most lightweight, simple equipment yet, while simultaneously supporting the short 12-month span between FID and first gas.
Delivery Date: 2023
Client: Exmar
End User: Eni S.p.A
Equipment:
19X BarLinks, including 2 spares
22X BarMoor Quick Connectors, including 2 spares
3X 80Te Chain Jack Assemblies
Service Life: 15 years
Location: Republic of Congo
Certifying Authority: Bureau Veritas Marine Division