Cote Mateve Spread Mooring System with Ship-to-Ship Connectors

The Cote Mateve Spread Mooring system with Ship-to-Ship Connectors brought together the Tango FLNG and Excalibur FSU with a split mooring configuration – an industry first for a floating LNG terminal. This project’s tight timeline led to the development of the BarMoor® and BarLink mooring options, providing our most lightweight, simple equipment yet, while simultaneously supporting the short 12-month span between FID and first gas. 

Delivery Date: 2023

Client: Exmar

End User: Eni S.p.A

Equipment:
19X BarLinks, including 2 spares
22X BarMoor Quick Connectors, including 2 spares
3X 80Te Chain Jack Assemblies

Service Life: 15 years

Location: Republic of Congo

Certifying Authority: Bureau Veritas Marine Division

Cote Mateve Spread Mooring System