Cote Mateve Spread Mooring System with Ship-to-Ship Connectors

The Cote Mateve Spread Mooring system with Ship-to-Ship Connectors brought together the Tango FLNG and Excalibur FSU with a split mooring configuration – an industry first for a floating LNG terminal. This project’s tight timeline led to the development of the BarMoor and BarLink mooring options, providing our most lightweight, simple equipment yet, while simultaneously supporting the short 12-month span between FID and first gas. 

Delivery Date: 2023

Client: Exmar

End User: Eni S.p.A

Equipment:
19X BarLinks, including 2 spares 
22X BarMoor Quick Connectors, including 2 spares
3X 80Te Chain Jack Assemblies

Service Life: 15 years

Location: Republic of Congo

Certifying Authority: Bureau Veritas Marine Division

Cote Mateve Spread Mooring System